Phase 2 of our kitchen (phase 1 was demolition and placing the big beam!) had Kevin tearing out the remaining cabinets and building walls. Part of the process also included enclosing part of the garage to be an 'addition' to the kitchen for a laundry room. (one of my favorite parts!) So far, he's taken out a false ceiling, and two walls...built three walls and rebuilt a half-wall. He's rewired the kitchen, built a dormer (with soon to be skylight) and installed cabinets and appliances. I picked out a few photos to show progress. The last photo shows my least favorite part of the remodel, washing dishes in the bathtub...good times!
Kev started demolition on Jan 3 and installed the last appliance, on March 31. I say three months is an excellent pace for doing most of the work by yourself!
On to phase three!